SITE VISITS:
07 15 2006
09 18 2006
>
09 19 2006
>
09 20 2006
>
09 21 2006
>
09 22 2006
>
09 26 2006
>
09 28 2006
>
10 04 2006
>
10 05 2006
>
10 10 2006
>
10 12 2006
>
10 17 2006
>
10 20 2006
>
10 30 2006
>
11 03 2006
>
10 30 2006 ALL POLES UP >
All 25 poles are now standiing. The concrete stamping is also complete. The orange canvas is protecting the formwork for the benches.